July 4, 2026
ga-court-revives-electrocution-suit-against-engineering-firm

The Georgia Court of Appeals has officially overturned a lower court’s decision, breathing new life into a personal injury lawsuit filed by a veteran lineman who suffered catastrophic injuries due to an electrocution incident at a Georgia Power substation. The appellate court’s ruling, delivered on Thursday, centers on the pivotal legal determination that Burns & McDonnell Engineering Co., acting as a project coordinator, owed a specific duty of care to the workers on-site, despite not being the direct employer of the injured party. This decision marks a significant development in the interpretation of third-party liability within the high-stakes environment of utility infrastructure and electrical engineering.

The case, which has been closely watched by both the legal community and the construction industry, underscores the complexities of safety responsibilities in multi-employer worksites. At the heart of the dispute is an incident that occurred during a complex maintenance and upgrade project at a Georgia Power substation. The plaintiff, a lineman tasked with executing technical maneuvers on high-voltage equipment, was severely burned and incapacitated when he came into contact with an energized component that was purportedly scheduled to be de-energized.

In its comprehensive opinion, the Georgia Court of Appeals found that the trial court erred in granting summary judgment to Burns & McDonnell. The lower court had previously ruled that the engineering firm could not be held liable because it did not exercise direct "control" over the lineman’s specific movements or the immediate physical environment. However, the appellate judges disagreed, pointing to the firm’s contractual obligation to coordinate power outage planning—a role they deemed central to the safety of every individual working within the substation’s perimeter.

The Nature of the Incident and Initial Litigation

The litigation stems from a 2022 accident that occurred during a planned system upgrade. According to court documents, the project involved multiple layers of contractors and subcontractors. Georgia Power had retained Burns & McDonnell to provide engineering and coordination services, which included the development of detailed "switching orders" and the synchronization of outages to allow for safe work transitions.

On the day of the accident, the plaintiff was working under the assumption that the specific sector of the substation had been successfully isolated and grounded. Evidence presented during the initial discovery phase suggested a breakdown in communication regarding the status of the electrical load. When the lineman approached the equipment, an arc flash occurred, resulting in third-degree burns over a significant portion of his body and permanent neurological damage.

The lawsuit filed by the lineman alleged that Burns & McDonnell was negligent in its oversight of the outage schedule. The complaint argued that as the party responsible for the "coordination" of the outage, the firm had a non-delegable duty to ensure that the information provided to field crews was accurate and that the timing of the de-energization was strictly adhered to.

Burns & McDonnell initially succeeded in having the case dismissed by arguing that their role was purely administrative and consultative. They maintained that the actual physical safety measures—such as "lockout/tagout" procedures and voltage testing—were the sole responsibility of the on-site contractors and the utility owner. They argued there was no "privity of contract" between the engineering firm and the individual lineman that would create a legal duty of care.

The Appellate Court’s Reasoning: Expanding the Scope of Duty

The reversal by the Georgia Court of Appeals hinges on the principle that a professional firm’s duty can extend to third parties if the firm’s specific professional services are intended to protect those parties from foreseeable harm. The court noted that in the context of high-voltage electrical work, "coordination" is not merely a clerical task but a critical safety function.

"The planning of a power outage in a high-voltage environment is inextricably linked to the physical safety of the personnel on the ground," the court stated in its opinion. "When an engineering firm assumes the responsibility of coordinating these outages, it assumes a duty to perform that task with the standard of care expected of professionals in that field, knowing that a failure to do so poses a direct threat of death or serious bodily injury."

The court further clarified that the lack of direct supervision over the plaintiff did not absolve the firm of liability. By managing the timeline and the flow of information regarding which circuits were live and which were dead, Burns & McDonnell held the "keys to the gate" regarding the safety of the workspace. This "functional control" over the environment’s safety parameters was deemed sufficient to establish a duty of care under Georgia tort law.

Chronology of the Case and Project Timeline

To understand the weight of this ruling, one must look at the timeline of the project and the subsequent legal battle:

  • January 2021: Georgia Power initiates a multi-million dollar substation modernization project. Burns & McDonnell is contracted to provide engineering, procurement, and coordination services.
  • March 2022: The project enters its most critical phase, requiring frequent "hot-to-cold" transitions where parts of the grid are taken offline to allow manual labor.
  • June 14, 2022: The accident occurs. The plaintiff is injured while working on a transformer that remained energized despite the outage plan indicating it should have been isolated.
  • Late 2022: The plaintiff files a formal complaint in a Georgia Superior Court, naming several entities, including Burns & McDonnell.
  • 2024: The trial court grants summary judgment in favor of Burns & McDonnell, effectively removing them from the case.
  • Late 2024 – Early 2025: The plaintiff’s legal team files an appeal, arguing that the trial court applied an overly narrow definition of "duty."
  • July 2, 2026: The Georgia Court of Appeals officially reverses the summary judgment, reinstating the engineering firm as a primary defendant.

Supporting Data: The Rising Risks in Utility Infrastructure

The revival of this suit comes at a time when the utility industry is seeing a rise in complex, multi-contractor projects. Data from the Bureau of Labor Statistics (BLS) and the Occupational Safety and Health Administration (OSHA) highlights the inherent dangers of this field.

According to OSHA, electrocution remains one of the "Fatal Four" leading causes of death in the construction and utility industries. In the last five years, electrical injuries have accounted for approximately 5% to 7% of all workplace fatalities in the United States. Furthermore, "failure to communicate" and "improper lockout/tagout procedures" are consistently cited among the top ten most frequent OSHA violations in substation environments.

Industry analysts note that as the U.S. electrical grid undergoes massive upgrades to accommodate renewable energy and increased demand, the reliance on third-party engineering firms for "coordination" has grown by nearly 30% since 2018. This case sets a precedent that these firms cannot simply shield themselves behind their consultant status when a failure in their planning leads to physical harm.

Official Reactions and Industry Implications

While Burns & McDonnell has not issued a formal statement following the appellate court’s decision, sources close to the defense suggest they are considering an appeal to the Georgia Supreme Court. The firm has consistently maintained that its role was limited to high-level scheduling and that the "on-the-ground" safety protocols were the responsibility of the field supervisors.

Conversely, legal representatives for the injured lineman hailed the decision as a landmark victory for worker safety. "This ruling sends a clear message to the entire industry: if you are paid to plan for safety, you are responsible for the results of that plan," said a spokesperson for the plaintiff’s legal team. "You cannot design the safety protocols for a hazardous worksite and then claim you have no responsibility when those protocols fail and a man’s life is destroyed."

The broader implications for the engineering and construction management sectors are profound. For decades, many firms have utilized "limitation of liability" clauses and "scope of work" definitions to distance themselves from site accidents. The Georgia Court of Appeals’ decision suggests that in inherently dangerous occupations—such as electrical utility work—the law may prioritize public safety and the "foreseeability of harm" over the strict language of a corporate contract.

Analysis: A Shift in Third-Party Liability

This case represents a subtle but powerful shift in how courts view the "professional duty" of engineering firms. Traditionally, an architect or engineer was only liable to their client (the property owner). However, modern legal trends are increasingly recognizing the "Restatement (Second) of Torts § 324A," which posits that one who undertakes to render services to another which he should recognize as necessary for the protection of a third person is liable to that third person for physical harm resulting from his failure to exercise reasonable care.

In this instance, the court applied this logic to the "coordination" of power outages. By taking on the task of deciding when and where power would be cut, Burns & McDonnell was effectively rendering a service necessary for the protection of the linemen.

For engineering firms, this means:

  1. Enhanced Risk Assessment: Firms must now conduct more rigorous internal audits of their coordination and communication protocols.
  2. Contractual Clarity: There will likely be a move to redefine "coordination" in contracts to either explicitly include or exclude safety oversight, though as this case shows, courts may ignore exclusions if the functional role implies a safety duty.
  3. Insurance Adjustments: Professional liability insurance (Errors and Omissions) may see premium increases as the "shield" against personal injury claims weakens.

Conclusion

The Georgia Court of Appeals’ decision to revive the suit against Burns & McDonnell Engineering Co. serves as a stark reminder of the legal weight carried by project management and coordination roles. As the case moves back to the trial court, the focus will shift from the legal definition of "duty" to the factual question of whether the firm’s specific actions—or lack thereof—constituted a breach of that duty.

The outcome of the upcoming trial will likely set a further benchmark for how "coordination" is defined in the utility sector. For the injured lineman, the ruling provides a path toward potential compensation for a lifetime of medical needs. For the engineering industry, it provides a sobering mandate to ensure that the "planning" of safety is treated with the same rigor as the execution of it. As infrastructure projects continue to grow in complexity and scale, the legal system appears increasingly unwilling to allow the architects of those projects to remain insulated from the human cost of technical failures.